Southwest Washington Regional Transportation Council

Project Showcase

NW 38th Avenue

Agency: Camas
Status: Right of Way
FHWA Aid#: 7031(004)
Project Type: Reconstruction: No Added Capacity
Description: Improve to 3-lane minor arterial standards with bike lanes and sidewalks.
Termini: NW Parker Street to Grass Valley Park
Project Length: 0.45 miles
  Federal Funds Project Cost Schedule Obligation
Preliminary Engineering $335,700 $1,015,700 January 15, 2022 July 24, 2020
Right of Way $904,100 $1,504,000 July 1, 2022 June 9, 2022
Construction $1,436,400 $3,399,300 July 1, 2024
Total $2,676,200 $5,919,000    

Project Photos

  • Before
  • Before

List of all projects.