I-5 High-Occupancy Vehicle Operational Study 

Executive Summary 
with Technical Advisory Committee Findings

April 2000


Outline

I. Background

II. Decision-Making Process

III. Selected HOV Option

IV. Key Findings

V. Bi-State Policy Issues


I. Background

The Regional Transportation Council (RTC), in conjunction with the Washington State Department of Transportation (WSDOT) and the Oregon Department of Transportation (ODOT), conducted an operational and feasibility study of High Occupancy Vehicle (HOV) lanes on I-5 between Clark County, Washington (134th Street), and Portland, Oregon. This was the next step of the Clark County Regional HOV Study, which identified a need to move forward with a more detailed feasibility and operational approach to implementing HOV facilities in the I-5 corridor. The study was charged with developing an HOV option that could be implemented in the corridor without replacing the Interstate Bridge and without the construction of any widening through Delta Park. It also follows closely the successful I-5 Northbound HOV Lane Pilot Project implemented by ODOT in October 1998. That project currently carries 2,400 persons per lane per hour, more than either of the general purpose (GP) lanes, and saves 5-7 minutes per vehicle. It also has a 70 percent public approval rating.

This effort was also strategically coordinated with the imminent construction work in Washington to widen I-5 between Main Street and 99th Street (and eventually to 134th Street) to add another lane in each direction. The study findings will provide guidance to WSDOT regarding the use of the new lane capacity.

The Base Case for this study was called the "No New HOV" alternative. It consisted of the current I-5 transportation network and projects contained in the Metropolitan Transportation Plan (MTP) outside of the I-5 Corridor. It also included the I-5 widening in Washington and the existing northbound HOV lane between Going Street and Delta Park in Oregon that operate during the PM peak period only. During the study process, several HOV strategies and alternatives were developed and considered. These included Queue Bypass options (no HOV on the Interstate Bridge, HOV lanes at selected locations in Washington and/or Oregon), a Delta Park only option (AM peak period), and a Full Corridor option which carried reversible HOV lanes across the Interstate Bridge.
A public opinion survey of 800 Clark County residents was conducted as part of the I-5 HOV Operational Study. The survey provided representative data of attitudes, knowledge, and behavior regarding HOV lanes.

The survey concluded that almost all bi-state travelers (96%) were aware of the existing northbound I-5 HOV lane. Two-thirds of those using the HOV lane reported saving travel time.

Slightly more than 50 percent supported HOV lanes as an effective traffic management strategy. Most respondents (59%) favored implementing HOV by adding the lane instead of converting an existing general purpose lane for HOV. Two-thirds supported peak-period operation of HOV lanes, while 23 percent supported 24-hours-a-day, 7-days-per-week operation of the HOV lane. Most of those surveyed (80%) agreed that the HOV lanes should have a strong enforcement program.

Return to top of page

II. Decision-Making Process

RTC was the project lead for the overall study and the management of work tasks. The I-5 HOV Technical Advisory Committee provided expertise and comment on the technical analysis and was made up of staff from the Washington State Department of Transportation, City of Vancouver, Clark County, C-TRAN, Metro, and the Oregon Department of Transportation. In addition, the two state transportation departments provided expert advice regarding the operation, design, and characteristics on HOV and their state facilities. Findings and recommendations of the TAC were forwarded to the Regional Transportation Advisory Committee for their comment and review prior to consideration by the RTC Board.

The RTC Board received the study finding and conclusions and forwarded them to the Bi?State Transportation Committee for their discussion. The role of the Bi-State Transportation Committee was to consider the study findings and conclusions and to recommend any bi-state action to the RTC Board and Joint Policy Advisory Committee on Transportation (JPACT) regarding an HOV facility in the I-5 corridor. Study findings will be forwarded to the I-5 Trade Corridor Study.

Figure ES-1. Decision-Making Process

Return to top of page

III. Selected HOV Option

After analysis and screening of several HOV options in the I-5 corridor, three non-bridge HOV options were evaluated for detailed operational analysis: Washington only HOV, Oregon only HOV and a bi-state HOV option consisting of an HOV facility in Washington and Oregon with no HOV on the Interstate Bridge. All HOV options resulted in travel time savings and higher HOV person demand than the base case, which has no AM southbound HOV. However, of the three options, the bi-state HOV option offered the highest travel time savings and HOV person demand. A bi-state HOV facility in the I-5 corridor resulted in significant mobility improvement in the corridor for transit and other shared ride users. 

Figure ES-2. Selected HOV Lane Configuration

The selected bi-state HOV option developed in the I-5 corridor is based on an analysis of traffic operations, safety, and design issues for the HOV options studied. The PM HOV option consists of the current NB HOV lane between Going Street and Marine Drive. The AM HOV option consists of a southbound HOV facility in Washington from 134th Street to Mill Plain Boulevard, no HOV lane across the Interstate Bridge, and an HOV lane in Oregon from Marine Drive to Lombard Avenue. The southbound AM option is described below:

WASHINGTON

Interstate Bridge No HOV lane across the bridge.

OREGON

Added capacity for HOV from Marine Drive to Lombard Avenue. The I-5 HOV Operational study's original goal was to analyze the feasibility of implementing an HOV lane without widening the corridor through Delta Park. The study examined accomplishing this via a reversible lane using a movable barrier. While the construction cost for such a concept would be lower than the cost of widening, ongoing operations and maintenance costs may eventually result in higher overall costs for the reversible lane compared to widening. It was determined that HOV should not be implemented without a major widening of the corridor due to overall cost, safety, and operational concerns. Southbound HOV capacity should be provided by constructing an additional travel lane on Interstate 5 from the Delta Park interchange to Lombard Ave. This project is included in the Metro's Regional Transportation Plan (RTP) strategic plan and ODOT has begun preliminary work on the project. The project was also recommended by the I-5 Trade Corridor Leadership Committee.

PERFORMANCE OF SELECTED HOV ALTERNATIVE

The selected southbound HOV option compares favorably against the following performance measures:

  • HOV would save users one minute per mile and a minimum of 5 minutes overall (meets the total travel times savings, but not travel time savings per mile in 2003, well-met in 2020)
  • HOV lane is forecast to carry at least 600 vehicles per hour (would be met southbound in the opening year (2003) as well as in 2020)
  • The HOV lane is expected to carry more persons per hour than any adjacent GP lane (would be met southbound in 2003 as well as in 2020)
  • General purpose lanes are currently experiencing LOS E/F conditions for at least one peak hour in each peak direction.

Return to top of page

IV. Key Findings

Of the HOV options identified for detailed analysis, the bi-state HOV option had the most benefit to mobility in the I-5 corridor, by providing the highest travel time savings and HOV person demand. The analysis results are summarized in the following table:

AM 2 Hour: Summary of HOV Options1
Alternative Vehicles in HOV Lane Bus Ridership Persons in HOVs Persons per GP lane HOV Lane Time Savings (Minutes per Vehicle) HOV Lane Time Savings (Minutes per Mile)
Base-Case: No New HOV N/A 1,720 4,000 ---- ---- N/A
Washington only 1,4002 1,800 4,900 3,850 7-8 1.1
Oregon only HOV 1,000 1,760 4,370 3,600 1.8 0.7
HOV in Washington and Oregon 1,530 1,900 5,120 3,850 8-10 1.1-1.2

1 Measured at Marine Drive
2 Measured at Mill Plain Boulevard

In addition, the study finds that:

The study concluded that:

The I-5 Trade Corridor Study's Corridor Development and Management Plan should address these conclusions as part of the overall Bi-State decision-making process on the I-5 corridor, including the considerations for any new Columbia River crossing capacity. A summary matrix of the study findings and conclusions by segment is included at the end of the executive summary.

The following Agency Issues will need discussion and resolution prior to further consideration of an HOV configuration in the corridor:

Return to top of page

V. Bi-State Policy Issues

Table ES-1. 
Summary of I-5 HOV Operational Study Findings and Conclusions
Finding Conclusion
Bi-State Corridor
Bi-State I-5 HOV facility provides the greatest mobility of all alternatives studied.  A southbound, AM peak period HOV facility should be provided in the I-5 Bi-State corridor. In the PM peak, the current northbound HOV lane between Going Street and Delta Park is preferred. 
The I-5 Corridor is a National Priority Trade Corridor and HOV facilities should be considered within the context of the overall function of I-5. The I-5 Trade Corridor Study should receive and address these findings as part of the overall Bi-State decision-making process on the I-5 corridor.
Washington Portion
In 2020, southbound AM peak congestion occurs for most of the corridor between 134th Street and the Interstate Bridge.  The selected HOV option consists of an AM southbound HOV facility from 134th Street to Mill Plain Boulevard.
A southbound HOV lane between 134th Street and the Interstate Bridge and through Delta Park is projected to save HOV users approximately 8 to 10 minutes per vehicle compared to general purpose lanes in 2020, and over one minute per mile. Most of the projected HOV time savings occurs in Washington (7-8 minutes per vehicle). The minimum operable segment in the AM peak is from 78th Street to Mill Plain Boulevard.
The Interstate Bridge meters traffic in each direction, affecting downstream queues both currently and in 2020. No further consideration should be given for a northbound HOV lane in the PM peak on the Washington side. A northbound HOV lane north of the Interstate Bridge should be considered when congestion levels warrant an HOV lane or if and when the Interstate Bridge is replaced.
Interstate Bridge
The Interstate Bridge meters traffic in each direction, affecting downstream queues both currently and in 2020. The I-5 Trade Corridor Study should receive and address these HOV considerations for any new Columbia River crossing capacity.
Benefits gained by having a northbound reversible HOV lane on the Interstate Bridge are more than offset by the disbenefits of increased congestion in the southbound direction in the PM peak period. No further consideration should be given for a reversible HOV facility across the Interstate Bridge.
Any reversible lane option on the Interstate Bridge reduces travel lane width, impacts traffic operations, and is difficult to design and manage with an operating lift-span drawbridge. No further consideration should be given for a reversible HOV facility across the Interstate Bridge.
Oregon Portion
Approximately one mile of queuing, similar to that currently experienced, is expected through Delta Park in 2020. Design of HOV southbound through Delta Park requires resolution of design issues and the implementation of HOV through Delta Park should be implemented as part of major widening through Delta Park.
A reversible lane design option through Delta Park has a substandard design, lack of shoulders and left-hand merging areas, presenting significant safety and operational concerns along with significant ongoing operational costs. A southbound, AM peak period HOV lane through Delta Park should be accomplished via widening of the corridor to achieve three full-time through lanes within acceptable design standards.

Return to top of page


Prepared for:
Southwest Washington Regional Transportation Council

In Cooperation with:
Washington State Department of Transportation
Oregon Department of Transportation
C-TRAN
City of Vancouver
Clark County
Metro

Submitted by:
Parsons Brinckerhoff Quade and Douglas
David Evans and Associates
Pacific Rim Resources
HS Public Affairs
Innovative Transportation Concepts
HDR Engineering


Send mail to webmaster@rtc.wa.gov with questions or comments about this web site.
Copyright ©1992-2008, Regional Transportation Council, All Rights Reserved.
This page was last updated January 16, 2008.